Existing law vests the Public Utilities Commission (PUC) with regulatory authority over public utilities, including electrical corporations. Existing law requires the PUC to establish reasonable average and maximum target energization time periods, as defined, and a procedure for customers to report energization delays to the PUC, as provided. Existing law requires the PUC to require an electrical corporation to take remedial actions necessary to achieve the PUC's targets. This bill would require the PUC to require each electrical corporation to meet energization timelines or targets established pursuant to the above-described provisions or by PUC order. The bill would require the PUC to impose a penalty if an electrical corporation fails to meet an energization timeline or target approved or required by the PUC, as provided. This bill would require the PUC to designate an infrastructure-constrained energization area based on objective criteria, including limited distribution or transmission infrastructure relative to available electrical capacity or projected load growth, inland or desert geography, and extended energization timelines. The bill would require the PUC to adopt rules authorizing over-the-fence transactions within infrastructure-constrained energization areas when an electrical corporation cannot reasonably meet energization targets and other specific conditions are met, as specified. The bill would require the PUC, in coordination with the State Energy Resources Conservation and Development Commission (Energy Commission) and local jurisdictions, to establish procedures to facilitate expedited development of electrical generation and energy storage facilities in infrastructure-constrained energization areas, as specified. The bill would require the PUC, in coordination with the Energy Commission, the Office of Land Use and Climate Innovation, and local jurisdictions, to establish procedures to facilitate expedited permitting, siting, and construction of electrical infrastructure owned or operated by an electrical corporation within infrastructure-constrained energization areas, as specified. The bill would require the PUC and the Energy Commission to coordinate with, and advocate before, the Independent System Operator (ISO) for expedited review and prioritization of projects in infrastructure-constrained energization areas, as specified. Existing law establishes the ISO as a nonprofit, public benefit corporation to ensure efficient use and reliable operation of the transmission grid and to manage the transmission grid and related energy markets, as specified. This bill would require the ISO to consider regional economic development needs, infrastructure constraints, and statewide policy objectives when conducting transmission planning and interconnection processes. The bill would require the ISO seek to streamline review and approval processes for projects located within infrastructure-constrained energization areas, as specified, and would require the ISO to annually report to the PUC and the Legislature on transmission and interconnection constraints affecting infrastructure-constrained energization areas. The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. This bill would exempt from the requirements of CEQA the approval of an electrical generation or energy storage project located within an infrastructure-constrained energization area if specific conditions are met, as provided. The bill would require the Office of Land Use and Climate Innovation to develop guidelines for the implementation of these provisions. Because a lead agency would be required to determine whether a project would qualify for this exemption, this bill would impose a state-mandated local program. Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime. Because certain of the above-described provisions would be part of the act and a violation of a PUC action implementing the above-described provisions would be a crime, this bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for specified reasons.
Existing law requires the State Energy Resources Conservation and Development Commission (Energy Commission) and the Public Utilities Commission (PUC) , on or before December 15, 2022, and quarterly thereafter, to submit to the Legislature a joint Reliability Planning Assessment that, among other things, includes prospective information on existing and expected resources, including updates on the interconnection status for renewable projects and any delays in interconnection, and expected retirements for both system and local resources. Existing law requires the Energy Commission to report in the energy almanac on California energy resources that serve load in California. This bill would require that the assessment also include the status of utility transmission upgrades and electrical grid infrastructure capacity and PUC approvals of applications for certificates of public convenience and necessity and permits to construct utility and independent projects, as specified.
(1) Existing law requires the Public Utilities Commission (PUC) , in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission) , to provide transmission-focused guidance to the Independent System Operator (ISO) about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the ISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified. On December 23, 2022, the PUC, the Energy Commission, and the ISO entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure. Existing law requires the Energy Commission and the PUC, in coordination with the ISO, every 5 years, to review the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the state's energy goals. This bill would require those entities, on or before January 1, 2028, to update the memorandum and workplan to, among other things, ensure that the memorandum and workplan reflect the requirements of Federal Energy Regulatory Commission Order 1920, as applicable. (2) Existing law vests the PUC with regulatory authority over public utilities, including electrical corporations. Existing law requires the PUC to identify a diverse and balanced portfolio of resources needed to ensure a reliable electricity supply that provides optimal integration of renewable energy and resource diversity in a cost-effective manner, as specified. This bill would require that the portfolio provide optimal integration in a cost-effective and risk-prudent manner, as specified. (3) Existing law requires that the above-described transmission-focused guidance provided to the ISO provide projections each year to support planning and approvals by the ISO in its annual transmission planning process, including projections of resource portfolios and electricity demand by region for at least 15 years into the future, as specified. Existing law expresses the state policy that planning for new transmission facilities include consideration of the goal of increasing systemwide reliability and cost efficiency, among other state policy goals. This bill would require that the transmission-focused guidance takes into account uncertainty and optionality, is risk prudent, and supports compliance with Federal Energy Regulatory Commission orders, as specified. The bill would remove the requirement that the projections be provided annually and would require the projections of resource portfolios and electricity demand by region to be for at least 20, rather than 15, years into the future. The bill would add to those state policy goals reducing resource interconnection timelines and supporting achievement of the state's energy, climate change, and air quality goals. (4) This bill would incorporate additional changes to Section 454.57 of the Public Utilities Code proposed by AB 2369 to be operative only if this bill and AB 2369 are enacted and this bill is enacted last. (5) Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime. Because certain provisions of this bill would be a part of the act and because a violation of a PUC action implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law authorizes a community choice aggregator to aggregate the electrical load of interested electricity consumers within its boundaries and requires a community choice aggregator to file an implementation plan with the Public Utilities Commission, to register with the commission, and to enter into an operating service agreement with an electrical corporation. Existing law requires the Energy Unit within the Governor's Office of Business and Economic Development to establish a Transmission Infrastructure Accelerator (accelerator) to develop a financing and development strategy for eligible transmission projects, as defined, to receive California Transmission Accelerator financing, and requires the accelerator to take the necessary steps to accelerate the development and deployment of those projects to maximize ratepayer savings. This bill would authorize a community choice aggregator to sponsor, develop, finance, construct, operate, lease, purchase, and own an eligible transmission project, regardless of whether the electrical transmission lines are used for the purpose of conveying electricity to the customers of the community choice aggregator. Under existing law, a violation of an order, decision, rule, direction, demand, or requirement of the commission is a crime. Because a violation of a commission action implementing the provisions of this bill would be a crime, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires the commission, in consultation with the Independent System Operator, to establish resource adequacy requirements for all load-serving entities, as provided. Existing law defines load-serving entity, for that purpose, as an electrical corporation, electric service provider, or community choice aggregator. Existing law requires each load-serving entity to be subject to the same requirements for resource adequacy, the renewables portfolio standard program, and the integrated resource planning process that apply to electrical corporations, as provided. This bill would require the commission to authorize a load-serving entity to elect to demonstrate compliance with resource adequacy requirements by selling to, or otherwise making transactions with, another load-serving entity, and would require those transactions to not represent more than 25% of a load-serving entity's compliance obligations and be of a short-term duration. The bill would require the commission to authorize those transactions to be denominated in the same unit of time used to denominate resource adequacy compliance requirements. The bill would authorize the commission to suspend or adjust that authority of a load-serving entity to sell to, or otherwise make transactions with, another load-serving entity, as specified. Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime. Because the above provisions would be a part of the act, and because a violation of a commission action implementing the above prohibition would be a crime, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.
Existing law vests the Public Utilities Commission (PUC) with regulatory authority over public utilities, including electrical corporations. Existing law requires the PUC to adopt a process for each load-serving entity to file an integrated resource plan, and a schedule for periodic updates to the plan, as provided. Existing law requires the PUC, in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission) and the Independent System Operator (ISO) , to determine if there is a need for the procurement of eligible energy resources based on a review of the integrated resource plans. This bill would require the PUC, when requiring procurement of resources under an integrated resource plan, to account for the ability of energy-only resources to achieve required clean energy deployment rates, to charge storage resources during off-peak periods, and to increase resource diversity, and would require the PUC to enable energy-only resources to satisfy procurement requirements to the maximum extent feasible. Existing law requires the PUC, in consultation with the Energy Commission, to provide transmission-focused guidance to the ISO about resource portfolios of expected future renewable energy resources and zero-carbon resources, as specified, to allow the ISO to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers. This bill would require the PUC and the Energy Commission to identify cost-effective opportunities to enable planned or operating energy-only resources to obtain deliverability through transmission capacity expansions, and to request the ISO to reserve associated deliverability for geothermal and wind. The bill would require the commission to designate energy-only resources as long lead-time resources for purposes of the ISO's scoring in its interconnection process, as specified. This bill would incorporate additional changes to Section 454.52 of the Public Utilities Code proposed by AB 2476 to be operative only if this bill and AB 2476 are enacted and this bill is enacted last. This bill would incorporate additional changes to Section 454.57 of the Public Utilities Code proposed by AB 2111 to be operative only if this bill and AB 2111 are enacted and this bill is enacted last.
Existing law provides that it is the policy of the state that each electrical corporation upgrade the state's electrical distribution systems as needed. Existing law requires the Public Utilities Commission (PUC) , in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission) and the Independent System Operator (ISO) , to take specified actions to facilitate the commercialization of microgrids for distribution customers of large electrical corporations. This bill would require the Governor's Office of Business and Economic Development, in conjunction with the ISO, to identify six electrical infrastructure modernization zones, as provided. The bill would require the PUC and the Energy Commission to recognize these zones as load growth priority areas. The bill would authorize an electrical corporation that serves a customer within an electrical infrastructure modernization zone to work with the local jurisdiction to update its electrical load projections. The bill would require the PUC to authorize an electrical corporation that serves a customer within an electrical infrastructure modernization zone to expedite cost recovery and to manage microgrids, as specified. Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime. Because the provisions of this bill would be a part of the act, and because a violation of a PUC action implementing its requirements would be a crime, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason. This bill would make legislative findings and declarations as to the necessity of a special statute for the unincorporated area known as Altadena in the County of Los Angeles.
Existing law requires the Public Utilities Commission (PUC) , in consultation with the State Energy Resources Conservation and Development Commission (Energy Commission) , on or before March 31, 2024, to provide transmission-focused guidance to the Independent System Operator about resource portfolios of expected future renewable energy resources and zero-carbon resources, including the allocation of those resources by region based on technical feasibility and commercial interest in each region to allow the Independent System Operator to identify and approve transmission facilities needed to interconnect resources and reliably serve the needs of load centers, as specified . On December 23, 2022, the PUC, Energy Commission, and Independent System Operator entered into a memorandum of understanding related to resource and transmission planning, transmission development and permitting, procurement, and interconnections in order to achieve reliability and policy needs and to coordinate the timely development of resources, resource interconnections, and needed transmission infrastructure. Existing law requires the Energy Commission and PUC, in coordination with the Independent System Operator, every 5 years, to review and update, as necessary, the memorandum of understanding and a related workplan to ensure the memorandum and workplan reflect the coordination that is needed to help meet the state's energy goals. This bill would require those entities to review and update, as necessary, the memorandum every 3 years, rather than every 5 years.
Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations. Existing law requires electrical corporations to submit information to the commission for various purposes, as provided. This bill would require the commission, on or before December 31, 2026, to produce a report identifying opportunities and needs to provide for local and system reliability with firm zero-carbon resources over the short term, midterm, and long term, as provided. The bill would require the report to include, among other things, characterization of the resource attributes vital for local and system reliability and identification of barriers, including market barriers, to deploying firm zero-carbon resources to enhance local and system reliability. Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime. Because the provisions of this bill would be a part of the act and because a violation of a commission action implementing those provisions would be a crime, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.
(1) Existing law provides for the establishment of an Independent System Operator (ISO) as a nonprofit public benefit corporation and requires the ISO to ensure efficient use and reliable operation of the electrical transmission grid consistent with achieving planning and operating reserve criteria no less stringent than those established by the Western Electricity Coordinating Council and the North American Electric Reliability Council. Existing law, the Clean Energy and Pollution Reduction Act of 2015, provides for the transformation of the ISO into a regional organization, with the approval of the Legislature, pursuant to a specified process. That process provides that modifications to the ISO's governance structure, through changes to its bylaws or other corporate governance documents, will not become effective until the ISO, the Public Utilities Commission (PUC) , the State Energy Resources Conservation and Development Commission (Energy Commission) , the State Air Resources Board (state board) , the Governor, and the Legislature take specified actions on or before January 1, 2019. This bill would delete the above-described provisions providing for the transformation of the ISO into a regional organization. The bill would authorize the ISO and the electrical corporations that are participating transmission owners whose transmission systems are operated by the ISO to use voluntary energy markets governed by an independent regional organization, only if specified requirements are satisfied. The bill would authorize the ISO, on or after January 1, 2028, to implement tariff modifications accepted by the Federal Energy Regulatory Commission to operate the energy markets whose rules are governed by an independent regional organization if the governing board of the ISO adopts a resolution, as specified, finding that each of the specified requirements have been, or will be, adopted by the independent regional organization. The bill would require the ISO to maintain the necessary technical capability to operate energy markets, as specified, and would require the ISO to continue its functions and responsibilities as a balancing authority, as provided. This bill would establish the Regional Energy Market Oversight Council, which would be responsible for ensuring that participation in regional energy markets serves the interests of the state. The bill would require the council to approve or disapprove initial participation in the independent regional organization by electrical corporations and any other participating load-serving entities and determine whether electrical corporations and any other participating load-serving entities should be required to withdraw from an energy market governed by the independent regional organization. The bill would require the council to convene a duly noticed public meeting to make a finding of approval or withdrawal of participation in the independent regional organization and would require the council to disapprove of initial participation in the independent regional organization, or order withdrawal, if the council makes any of specified findings. (2) Existing law establishes the California Renewables Portfolio Standard Program, which requires the PUC to establish a renewables portfolio standard requiring all retail sellers, as defined, to procure a minimum quantity of electricity products from eligible renewable energy resources, as defined, at specified percentages of the total kilowatthours sold to their retail end-customers during specified compliance periods. Existing law defines "California balancing authority" and "balancing authority area" for purposes of the program. This bill would provide that the above-described independent regional organization is not a California balancing authority and its geographic footprint is not a balancing authority area for purposes of the program. The program, consistent with the goals of procuring the least-cost and best-fit eligible renewable energy resources that meet project viability principles, requires that all retail sellers procure a balanced portfolio of electricity products from eligible renewable energy resources, as specified, referred to as the portfolio content requirements. This bill would require, in making determinations regarding the eligibility of products to satisfy the portfolio content requirements, the Energy Commission to require, at a minimum, resources that do not have a first point of interconnection to a California balancing authority to demonstrate either that the resource operates under a pseudo-tie agreement or dynamic scheduling agreement with the Independent System Operator of another California balancing authority, or that the resource has secured, and exercised its rights to, firm transmission necessary to deliver its output to a California balancing authority without substituting electricity from another source. (3) Existing law requires the Power Exchange to provide an efficient competitive auction, open on a nondiscriminatory basis to all suppliers, that meets the loads of all exchange customers at efficient prices, and authorizes the Power Exchange governing board to form appropriate technical advisory committees composed of market and nonmarket participants to advise the governing board on relevant issues. This bill would delete these provisions. (4) Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the PUC is a crime. Because certain provisions of this bill would be part of the act and a violation of a PUC action implementing the bill's requirements would be a crime, the bill would impose a state-mandated local program. The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement. This bill would provide that no reimbursement is required by this act for a specified reason.