State Corporation Commission; cost allocation proceedings for certain electric utilities.
What changed between versions
Section 1 was modified to include 'current and proposed allocations' and 'retail customers or electric service providers receiving transmission service' in addition to the original language, broadening the scope of the cost allocation review.
Section 1 was modified to add language requiring that data center transmission projects be presumed to serve data centers unless demonstrated otherwise by clear and convincing evidence, adding a burden of proof requirement.
A new Section 4 was added providing formal definitions for 'Data center', 'Phase I Utility', 'Phase II Utility', and 'Transmission costs' to ensure consistent interpretation throughout the bill.
Original introductory text including bill number, filing dates, and committee referral information was removed and replaced with substitute bill formatting conventions.