Electric utilities; electric grid utilization metrics; State Corporation Commission.
What changed between versions
The deadline for utilities to petition for grid utilization metrics was moved from November 1, 2026, to October 15, 2026.
Utilities are now permitted to consolidate their grid utilization petition with their 2026 integrated resource plan filing.
The requirement for utilities to provide detailed calculation methodologies was replaced with a requirement to provide an overview of industry-standard metrics.
The commission must now analyze a broader range of non-wires alternatives, including flexible transmission, synchronous condensers, and power quality monitoring for large customers.
The specific mandate for the commission to issue a final order by July 1, 2027, was removed.
The commission's authority to determine how metrics are applied and reported was expanded to include future integrated resource plan filings.