Permit applications for natural gas pipelines; State Water Control Law. Requires applicants for federal licenses or permits for natural gas transmission pipelines with an inside diameter of at least 24 inches to submit a separate application, erosion and sediment control plan, and stormwater management plan to the Department of Environmental Quality concurrently with a Joint Permit Application. Current law requires such application standards for pipelines with an inside diameter of greater than 36 inches. The provisions of the bill apply to any natural gas transmission pipeline project of at least 24 inches in inside diameter that is subject to a certificate of public convenience and necessity under the federal Natural Gas Act and that has not commenced construction by July 1, 2024, notwithstanding any previous certification previously issued or waived by the Department of Environmental Quality or the State Water Control Board.
Bill status in committee 1 of 4 stages cleared
Introduction
Jan 2024
Committee Review
Floor Vote
Governor
Introduced Jan 8, 2024 Last action Nov 18, 2024
Floor votes

How they voted

No floor votes recorded yet.
Full legislative history

Actions timeline

Total actions
7
Key actions
1
Committee
3
Jan 29, 2024
Lower · Passed
Subcommittee recommends continuing to 2025 (Voice Vote)
lower
Jan 23, 2024
Committee
Assigned ACNR sub: Chesapeake
lower
Jan 8, 2024
Committee
Referred to Committee on Agriculture, Chesapeake and Natural Resources
lower
1 primary · 6 co-sponsors

Sponsors