Underground transmission lines; qualifying projects.
Summary
Pilot program for underground transmission lines; qualifying projects. Authorizes the State Corporation Commission to, in reviewing any application submitted by a public utility for a certificate of public convenience and necessity for the construction of an electrical transmission line of 500 kilovolts filed between January 2025 and July 2032, approve up to two applications for qualifying projects to be constructed in whole or in part underground as part of the pilot program for underground transmission lines and to provide an expedited review of any such application. The bill removes certain provisions related to the existing pilot program. Under the bill, a project shall be qualified if an engineering analysis demonstrates that it is technically feasible, if the applicant provides an overall cost of the project and its impact on electric service rates, and if the governing body of each locality in which a portion of the proposed line will be placed underground indicates support for the transmission line to be placed underground. The bill permits the Commission to deny an application for a project that otherwise meets the criteria to qualify, provided that the Commission shares its rationale for doing so. Additionally, rather than assigning certain costs to be recovered by Virginia jurisdictional customers, the bill requires that such costs be allocated by the Commission in a manner that is just and reasonable for customers.
Bill status
died
3 of 5 stages cleared
Introduction
Jan 2025
Committee Review
Feb 2025
House of Delegates Passage
Feb 2025
Senate Passage
Governor
Introduced Jan 17, 2025
Last action Feb 17, 2025
Maddy AI version diff · 2 comparisons
What changed between versions
Labor and Commerce Subcommittee Substitute
→
Labor and Commerce Substitute
·
5 edits
MODERATE
The bill text was reformatted from a plain text version to a structured legislative document with line numbers and proper headers. The substantive policy content regarding the underground transmission line pilot program appears unchanged, though the formatting includes some inconsistencies and placeholder text that may need cleanup.
TECHNICAL
Text was converted from plain text to a numbered legislative format with headers and line numbers
Removed header text 'OFFERED FOR CONSIDERATION' and added 'HOUSE SUBSTITUTE' with bill number and date
Added page number '25106431D' and bill reference 'HB2755H1'
Included timestamp '1/31/25 09:00' in the document
Added extra blank lines and spacing throughout the document
Floor votes · House of Delegates Feb 4, 2025
How they voted
49–48
Passed · 3 other
Total votes 100
Feb 4, 2025
D
Democratic51
96% Yea
R
Republican49
95% Nay
Vote distribution
All Yea
All Nay
Mixed
No data
Full legislative history
Actions timeline
Total actions
17
Key actions
2
Committee
6
Feb 17, 2025
Committee
Failed to report (defeated) in Commerce and Labor (6-Y 8-N)
upper
Feb 5, 2025
Committee
Referred to Committee on Commerce and Labor
upper
Feb 4, 2025
Lower · Passed
Read third time and passed House (49-Y 48-N)
lower
Jan 30, 2025
Lower · Passed
Reported from Labor and Commerce with substitute (12-Y 9-N)
lower
Jan 29, 2025
Committee
Assigned L & C sub: Subcommittee #4
lower
Jan 24, 2025
Committee
Assigned L & C sub: Subcommittee #3
lower
Jan 17, 2025
Committee
Referred to Committee on Labor and Commerce
lower
Jan 17, 2025
Introduced
Presented and ordered printed 25105325D
lower
1 primary · 3 co-sponsors
Sponsors
Role
Legislator
Party
State
District
P
J.J. Singh
DDemocratic
Co
Atoosa Reaser
DDemocratic
Co
David Reid
DDemocratic
Co
Kannan Srinivasan
DDemocratic
Ask Maddy
·
AI policy assistant
Ask Maddy about HB 2755
Scope: VA
Hi! I can help you understand HB 2755. What would you like to know?
Try one of these
i
Maddy answers using official bill text and legislative records. Always verify before sharing.
Sources cited inline