Data centers; site assessment for high energy use facility.
What changed between versions
New requirement added for electric utilities to submit information about substations and transmission voltage to localities before approval of new high energy use facilities.
The site assessment requirement was expanded from subsection B to cover both subsections B and C, and the language was modified to clarify that assessments should not impact State Corporation Commission authority.
The definition of 'high energy use facility' was modified to explicitly list the types of applications (rezoning, special exception, special use permit) when determining the 100 megawatt threshold.
The exemption for existing facilities was renumbered from subsection D to subsection F and reworded to clarify it applies to sites with existing legislative or administrative approval.