Eveleth; Progress Parkway construction project prior appropriation modified.
This bill modifies a prior appropriation for the Progress Parkway construction project in Eveleth, Minnesota, allowing $6 million from the state's general fund to be used for various project phases. The funds will support design, engineering, environmental analysis, land acquisition, and construction work to improve intersections and extend the road from Highway 53 to Trunk Highway 37. The appropriation is designated as a one-time allocation available until June 30, 2030, and will be distributed through grants to St. Louis County for implementation. This legislation updates the existing funding framework established in 2023 to extend the project timeline and ensure continued financial support.
Bill status
passed
3 of 5 stages cleared
Introduction
Mar 2026
Committee Review
May 2026
House Passage
May 2026
Senate Passage
Governor
Introduced Mar 5, 2026
Last action May 5, 2026
Floor votes · House May 4, 2026
How they voted
129–0
Passed
Total votes 129
May 4, 2026
D
Democratic62
100% Yea
R
Republican67
100% Yea
Vote distribution
All Yea
All Nay
Mixed
No data
Full legislative history
Actions timeline
Total actions
10
Key actions
3
Committee
3
May 5, 2026
Committee
Referred to Finance
upper
May 5, 2026
Introduced
Introduction and first reading
upper
May 5, 2026
Introduced
Received from House
upper
May 4, 2026
Lower · Passed
Bill was passed
lower
Apr 22, 2026
Lower · Passed
Committee report, to adopt
lower
Apr 7, 2026
Lower · Passed
Committee report, to adopt and re-refer to Ways and Means
lower
Mar 5, 2026
Introduced
Introduction and first reading, referred to Transportation Finance and Policy
lower
1 primary · 1 co-sponsor
Sponsors
Ask Maddy
·
AI policy assistant
Ask Maddy about HF 4006
Scope: MN
Hi! I can help you understand HF 4006. What would you like to know?
Try one of these
i
Maddy answers using official bill text and legislative records. Always verify before sharing.
Sources cited inline