HB 4971 West Virginia House of Delegates · 2026 Regular Session

Relating to preliminary planning for future electric substations near industrial parks on certain high voltage transmission lines

HB 4971 requires new high-voltage electric transmission lines (400kV or greater) needing West Virginia Public Service Commission approval to include a substation near industrial parks if the line runs within five miles of one. It limits this requirement to one substation per 40-mile segment of the line within the state, with the substation needing completion within two years after the line becomes operational. The law applies to transmission developers and the Public Service Commission, aiming to boost economic development by linking grid infrastructure directly to industrial areas. Key provisions include evaluating substation locations based on expected job creation and tax benefits, and prohibiting route choices designed to avoid industrial park proximity.
Bill status passed 3 of 5 stages cleared
Introduction
Jan 2026
Committee Review
Feb 2026
House of Delegates Passage
Feb 2026
Senate Passage
Governor
Introduced Jan 29, 2026 Last action Feb 26, 2026
Maddy AI version diff · 4 comparisons

What changed between versions

hb4971 hfa dillon howell 2-25 _1 adopted.htm hb4971 hfat anderson 2-25 adopted adopted.htm · 3 edits
MINOR
The bill's title was updated to reflect a new focus on high voltage transmission lines and substations, while a proposed amendment to exclude residential ratepayers from paying for related costs was removed.
Scope change
The bill's scope was expanded to explicitly include requirements for reports on substation proximity to business-ready sites and provisions for site preparation work, replacing the previous focus on a specific cost recovery exclusion.
REQUIREMENT

The bill now requires that reports regarding the proximity of electric substations to business-ready sites be included in applications for public convenience and necessity certificates.

New provisions allow for site preparation work on approved substations to be performed upon Public Service Commission approval.

FISCAL

A proposed amendment ensuring that cost recovery for work under the bill would not be borne by residential ratepayers was deleted.

Floor votes · House of Delegates Feb 25, 2026

How they voted

960
Passed · 4 other
Total votes 100
Feb 25, 2026
D Democratic9
8 Yea 1
88% Yea
R Republican91
88 Yea 3
96% Yea
Vote distribution
All Yea All Nay Mixed No data
Full legislative history

Actions timeline

Total actions
23
Key actions
4
Committee
2
Amendments
3
Feb 26, 2026
Introduced
Introduced in Senate
upper
Feb 25, 2026
Lower · Passed
Title amendment adopted (Voice vote)
lower
Feb 25, 2026
Lower · Passed
Passed House (Roll No. 184)
lower
Feb 25, 2026
Lower · Passed
Amendment adopted (Voice vote)
lower
Feb 25, 2026
Introduced
Amendment reported by the Clerk
lower
Feb 24, 2026
Introduced
Amendment pending
lower
Feb 24, 2026
Introduced
Amendment reported by the Clerk
lower
Feb 20, 2026
Lower · Passed
By substitute, do pass
lower
Jan 29, 2026
Committee
To House Energy and Public Works
lower
Jan 29, 2026
Introduced
Introduced in House
lower
1 primary · 10 co-sponsors

Sponsors