An act relating to testing of schools in Vermont for polychlorinated biphenyls
What changed between versions
New Section 1 directs ANR to cease and terminate all scheduled or ongoing indoor air quality PCB testing in public schools and approved/recognized independent schools constructed or renovated before 1980.
Exemption: the State will not pay for PCB investigation/removal if it was part of a planned renovation or construction project rather than a response to ANR testing. This exemption does not apply to the $16,000,000 reserved for Burlington School District under 2023 Acts No. 78 Sec. C.112.
Exception carved out: schools that previously tested positive for PCBs at levels requiring continued testing under state or federal law will continue to be tested, funded by the State.
The State of Vermont is required to pay for investigation, remediation, and removal of PCBs at any school where ANR completed testing and the result exceeded State school action levels, consistent with 2023 Acts and Resolves No. 78, Sec. C.112.
All remaining funds from prior PCB testing appropriations (2021 Acts No. 74 Sec. E.709.1, 2023 Acts No. 78 Sec. C.112, or any other) are redirected from testing to investigation, remediation, and removal at positive schools.
If State funds are insufficient for remediation at positive schools, the Secretary of Natural Resources must submit a funding request to the House and Senate Education, Environment/Natural Resources, and Appropriations Committees.
Schools that tested positive may stop interim remedial measures if: the State is not fully funding them, building replacement is the most viable remediation option, and federal law does not require immediate remediation.
The Commissioner of Health must review and update the assessment of health impacts on students and staff from airborne PCBs in schools and submit it to legislative committees by January 15, 2027.
The Secretary of Natural Resources must submit a long-term PCB remediation plan to legislative committees by January 15, 2027, after consultation with the Secretary of Education, school representatives, and other interested parties.
The deadline for schools to complete PCB testing was changed from July 1, 2027 (As Enacted) to August 1, 2035 (As Passed), an extension of approximately 8 years.
Beginning January 15, 2027 and annually thereafter, the Secretary of Natural Resources must submit a report to legislative committees covering: number of schools tested, remaining to be tested, positive results, remedial measures taken and planned, State funds expended, remaining funds, and estimate of additional funds needed.