SB 631 New Hampshire Senate · 2026 Regular Session

authorizing the sale of toll credits to fund a newly established noise barrier construction fund for the design and construction of noise barrier projects.

SB 631 directs the New Hampshire Department of Transportation to install a 1,845-foot sound barrier along the west side of Interstate 93 southbound, between Pillsbury Road in Londonderry and Exit 4 (Route 102 ramp). The barrier will border the Woodmont Development property and aims to reduce noise for nearby residents. The project has an estimated cost of $8.07 million, funded through existing Highway Fund and potential federal funds (if eligible), with no new state funding provided. This is a physical infrastructure project affecting properties adjacent to the specified I-93 corridor.
Bill status passed 3 of 5 stages cleared
Introduction
Nov 2025
Committee Review
Mar 2026
Senate Passage
Mar 2026
House Passage
Governor
Introduced Nov 25, 2025 Last action Mar 12, 2026
Maddy AI version diff · 1 comparison

What changed between versions

Introduced As Amended by the Senate · 6 edits
MODERATE
The bill was completely transformed from a narrow directive to build one specific sound barrier on I-93 southbound in Londonderry into a broad funding mechanism that authorizes the sale of up to $10 million per year in turnpike toll credits to create a dedicated Noise Barrier Construction Fund for noise barrier projects statewide. The original single-project approach with an estimated cost of about $8 million was replaced with a flexible, continually appropriated fund whose fiscal impact is now indeterminable because no market for selling toll credits yet exists.
SCOPE

The bill changed from directing DOT to build one specific 1,845-foot sound barrier on I-93 southbound in Londonderry to authorizing a general funding mechanism (Noise Barrier Construction Fund) for the design and construction of noise barrier projects that meet Type II criteria under DOT's existing policy guidelines.

The specific project details (Pillsbury Road to Exit 4 southbound off-ramp, approximately 1,845 feet along the Woodmont Development property line) were entirely removed.

FISCAL

A new restricted, nonlapsing fund called the Noise Barrier Construction Fund was created. The commissioner is authorized to sell up to $10,000,000 per year in turnpike toll credits, subject to federal rules, turnpike covenants, and approval by both the fiscal committee and the joint legislative capital project overview committee.

A new dedicated account (subparagraph 411) was added to RSA 6:12, I(b) to house moneys in the Noise Barrier Construction Fund.

TIMELINE

The effective date changed from 'upon its passage' to July 1, 2026.

ELIGIBILITY

Noise barrier projects must meet Type II noise barrier criteria set forth in DOT's Policy and Procedural Guidelines for the Assessment and Abatement of Highway Traffic Noise. The commissioner may consider additional adjustment factors after consultation with affected communities.

Floor votes

How they voted

No floor votes recorded yet.
Full legislative history

Actions timeline

Total actions
12
Key actions
5
Committee
5
Amendments
1
Mar 12, 2026
Upper · Passed
Ought to Pass: MA, VV; 03/12/2026; SJ 6
upper
Mar 5, 2026
Upper · Passed
Committee Report: Ought to Pass, 03/12/2026, Vote 7-0; SC 9
upper
Feb 5, 2026
Upper · Passed
Ought to Pass with Amendments #2026-0350s, and #2026-0487s, MA, VV; Refer to Finance Rule 4-5; 02/05/2026; SJ 3
upper
Feb 5, 2026
Introduced
Sen. Ricciardi Floor Amendment # 2026-0487s, AA, VV; 02/05/2026; SJ 3
upper
Feb 5, 2026
Upper · Passed
Committee Amendment # 2026-0350s, AA, VV; 02/05/2026; SJ 3
upper
Jan 28, 2026
Upper · Passed
Committee Report: Ought to Pass with Amendment # 2026-0350s, 02/05/2026; Vote 4-0; CC; SC 4
upper
Nov 25, 2025
Introduced
Introduced 01/07/2026 and Referred to Transportation; SJ 1