AN ACT relating to solar merchant electric generating facilities.
What changed between versions
Changed the section number from KRS 278.704 to KRS 278.710 for the construction certificate requirements.
Replaced specific setback distance requirements with a list of criteria the board must use to evaluate construction certificate applications.
Added special provisions for facilities located on former coal processing plants that use on-site waste coal as fuel, requiring compliance with specific setback rules.
Added new reporting requirements for construction certificate holders to file bond copies, construction completion notices, and incentive reports with the Energy and Environment Cabinet.
Added requirements for public meetings when transferring rights and obligations under construction certificates.
Changed the construction certificate validity period from three years to a 120-day or 180-day decision timeline for applications.