RELATING TO THE PUBLIC UTILITIES COMMISSION.
What changed between versions
Added a requirement for the commission to apply a presumption in favor of using historical cost trends and external indices rather than future cost projections when resetting utility revenues.
Updated the statutory list of factors the commission must consider when reviewing utility performance to include affordability, customer engagement, accessibility of system information, and renewable energy integration.
Confirmed that the commission may adopt alternative ratemaking procedures to establish performance-based rates, overriding traditional cost-based methods if needed.
Expanded the definition of 'performance-based incentives' to explicitly include revenue adjustment mechanisms, cost control mechanisms, rewards for superior performance, and penalties for subpar performance.
Changed the deadline for establishing performance-based incentives from January 1, 2020, to January 1, 2027.