RELATING TO ENERGY.
What changed between versions
The streamlined interconnection process is now limited to investor-owned electric utility companies instead of all regulated utilities.
Electric vehicle charging is now explicitly included as part of the grid-ready home interconnection process.
The requirement for utilities to pay a cost-sharing fee for service upgrades was removed; asset owners must now pay for these upgrades.
New requirements were added to establish a process for approving or certifying licensed electricians to perform specific meter and panel upgrades.
Reporting obligations were updated to require the Hawaii Electricity Reliability Administrator to report to the Legislature instead of the Public Utilities Commission.
The bill's summary and statutory references were updated to reflect the new focus on investor-owned utility companies.