RELATING TO REMEDIES.
What changed between versions
Clarified that the 10-year statute of repose applies to all types of construction defect claims, not just specific ones.
Updated notice requirements to specify exactly what information must be included in a claim notice, such as detailed descriptions of defects and damages.
Added a requirement that claimants must complete notice, offer, and inspection steps before joining a class action lawsuit.
Set specific timeframes for contractors to respond to claims (30 days) and for inspections to be completed (9 months).
Established a formal offer-and-settlement process where contractors must offer repairs or monetary settlement within a set period.
Clarified definitions for 'date of completion' and 'improvement' to determine when the statute of repose begins.