Optimizing Colorado Electric Transmission System
What changed between versions
Redefinition of 'Advanced Transmission Technologies' to explicitly include increasing capacity for renewable and zero-carbon resources and lowering costs.
New requirement for qualifying retail utilities to include an evaluation of advanced transmission technologies in their electric resource plans starting September 1, 2025.
Added requirement for utilities to submit detailed explanations if they do not incorporate advanced transmission technology evaluations, including cost-effectiveness analyses.
Study requirements now include specific goals such as reducing curtailment of renewable resources, reducing wildfire ignition risk, and increasing capacity for new renewable energy connections.
Bill title and purpose changed from general grid optimization to specific carbon emission reduction goals with interim targets.