underground facilities; excavations; notification
What changed between versions
The definition of a 'large project' was changed from meeting one of three criteria to meeting either of two criteria, specifically removing the requirement that the project include at least ten contiguous land parcels.
The exemption for single-family residential properties was removed from the general marking requirement, expanding the rule's applicability to include excavations on single-family homes.
The coordination meeting rules were updated to allow parties to decide if the meeting is virtual or on-site, rather than giving the excavator sole discretion.
New requirements were added for the one-call notification center to establish minimum technical and data security standards for its interactive positive response system.
The one-call notification center is now required to adopt the necessary rules and procedures within one year of the act's effective date.